Calendar shows dated items from Kanban and other project modules in one week, month or year view. Each source module owns its records; the only records you can create or change here are Kanban tasks.
On this page
What the calendar shows
Calendar is an aggregate view. It does not store its own events: each item is a date taken from a source module. Only open items appear; done, cancelled, closed and void records are left out.
- A Kanban task with different start and due dates appears twice: a start marker with an arrow, and the due item.
- Overdue marks items whose date has passed.
- Soon marks items dated within the next seven days.
- Australian public holidays are shaded green and tagged Hol.
Sources and record ownership
| Legend | Source module | Date shown | Opens |
|---|---|---|---|
| Task | Kanban | Start date and due date | Kanban board |
| RFI | RFI | Due date | RFI register |
| NCR | QA / NCR | Due date | NCR record |
| Defect | Defect List | Due date | Defect record |
| HSE | HSE | Earliest open action due date | Incident record |
| Roster | Roster | Crew swing starts and daily rostered-on count | Roster |
| Insurance | Contractor Insurance | Expiry of accepted policies for active project companies | Contractor Insurance |
| Holiday | Built-in Australian public holiday list | Holiday date | No link |
Users with Travel & Logistics access also see mobilise, demobilise and travel booking items under Roster. These open the Mobilisation view. Booking costs are never shown.
Gantt activities, milestones and Gantt non-working dates do not appear in Calendar.
Creating and editing items
To create a Kanban task from Calendar:
- Select a day.
- Select New Kanban Task.
- Enter a Title. Optionally add a description, change the Start date or Due date (both default to the selected day) and set Priority.
- Select Create Kanban Task.
The task is saved in the project's Kanban module. In the side panel, Kanban tasks show Rename and Delete icons. Delete removes the task from Kanban.
Create all other items in their own module. Expand Source events in other modules for links to the RFI, NCR and HSE registers.
Permissions
| Action | Permission needed |
|---|---|
| Open Calendar | Calendar: View |
| See travel and mobilisation items | Travel & Logistics: View |
| Create or rename a Kanban task | Kanban: Edit |
| Delete a Kanban task | Kanban: Admin |
Calendar is also available on a site, where it shows items from the site's own workspace. Access uses the higher of your site and project Calendar permission.
Calendar, Gantt and Kanban
- Kanban owns tasks and their workflow.
- Gantt owns the schedule, activities, dependencies and the project working calendar.
- Calendar shows dates from Kanban and other modules in one place. Use it to see what falls due on a given day.