3-week lookahead Gantt chart template

Fifteen working days of trade activities on a multi-storey building, with a pre-pour hold point and a rough-in inspection. Use it for the short-term plan that the site team reviews each week: the next three weeks of work broken into trade activities, so each trade knows when its area is ready and what must be signed off first.

It has 3 phases, 17 tasks and 2 milestones, joined by 20 links, and runs for 15 working days on a Monday to Friday week. The template opens below in the free Gantt chart maker, starting today. Change any task, then export a PNG, PDF or CSV or share a link. No account is needed.

  • Free, no sign-up
  • Tasks already linked
  • Critical path shown
  • Export PNG, PDF and CSV
Loading the Gantt chart maker…

Tasks in the 3-week lookahead template

Durations are in working days. Predecessors use the tool's row numbers: 3 means “starts after row 3 finishes”, and 4SS+2 means “starts two working days after row 4 starts”. A phase shows the span of the tasks inside it.

RowTaskTypeDuration (working days)PredecessorsOwner
1Structure: Level 3 slabPhase15
2Level 2 column formwork and reinforcementTask3Formworker
3Pour Level 2 columnsTask12Concreter
4Level 3 deck formworkTask43Formworker
5Level 3 slab reinforcementTask34SS+2Steel fixer
6In-slab conduits and penetrationsTask25SS+1Electrician
7Hold point: pre-pour inspectionMilestone05, 6Structural engineer
8Pour Level 3 slabTask17Concreter
9Cure slab and strip edge formsTask38Formworker
10Back-prop Level 2Task29Formworker
11Fit-out: Level 1Phase15
12Wall framingTask4Carpenter
13Plumbing rough-inTask412SS+2Plumber
14Electrical rough-inTask412SS+2Electrician
15Services rough-in inspectionMilestone013, 14Certifier
16Plasterboard delivery and load-inTask115FS-1Supplier
17Plasterboard sheetingTask615, 16Plasterer
18Set and sand plasterboardTask317FF+2Plasterer
19Paint first coatTask118Painter
20Site and logisticsPhase5
21Raise perimeter scaffold to Level 4Task28Scaffolder
22Start Level 3 column formwork for the next cycleTask321Formworker

Scroll the table sideways to see every column.

How to use this template

  1. 1. Set the dates. Move a task later and the tasks linked after it move with it. Weekends are skipped.
  2. 2. Rename and resize the tasks. Type over any task name or duration, add your own tasks and delete the ones you do not need.
  3. 3. Check the critical path. Tasks in red have no float. A delay to any of them moves the finish date.
  4. 4. Export or share. Download a PNG, PDF or CSV, or copy a share link. The chart also saves in this browser as you work.

If you already have a chart saved in this browser, the tool opens your chart and offers to load this template instead, so nothing is replaced without asking.

Run the schedule in TaskRox

The free tool is for one person planning one chart. TaskRox is construction project management software: the whole team works on the same live schedule, with baselines, Microsoft Project and Primavera P6 import, and schedule tasks linked to RFIs and daily reports.

Save your chart to TaskRox 14-day free trial, no credit card.