Product launch Gantt chart template

Research, build, marketing and launch day in one timeline. Use it to line up product build, beta testing and marketing so that launch day is set by the work that has to be ready first.

It has 4 phases, 9 tasks and 1 milestone, joined by 11 links, and runs for 32 working days on a Monday to Friday week. The template opens below in the free Gantt chart maker, starting today. Change any task, then export a PNG, PDF or CSV or share a link. No account is needed.

  • Free, no sign-up
  • Tasks already linked
  • Critical path shown
  • Export PNG, PDF and CSV
Loading the Gantt chart maker…

Tasks in the product launch template

Durations are in working days. Predecessors use the tool's row numbers: 3 means “starts after row 3 finishes”, and 4SS+2 means “starts two working days after row 4 starts”. A phase shows the span of the tasks inside it.

RowTaskTypeDuration (working days)Predecessors
1ResearchPhase8
2Market and customer researchTask5
3Positioning and pricingTask32
4BuildPhase18
5Product buildTask153
6Beta testingTask55FF+3
7MarketingPhase15
8Website and launch pageTask65SS+5
9Press and partner outreachTask88SS+2
10Sales enablementTask43
11LaunchPhase6
12Launch readiness reviewTask16, 8, 9
13Launch dayMilestone012
14Post-launch follow-upTask513

Scroll the table sideways to see every column.

How to use this template

  1. 1. Set the dates. Move a task later and the tasks linked after it move with it. Weekends are skipped.
  2. 2. Rename and resize the tasks. Type over any task name or duration, add your own tasks and delete the ones you do not need.
  3. 3. Check the critical path. Tasks in red have no float. A delay to any of them moves the finish date.
  4. 4. Export or share. Download a PNG, PDF or CSV, or copy a share link. The chart also saves in this browser as you work.

If you already have a chart saved in this browser, the tool opens your chart and offers to load this template instead, so nothing is replaced without asking.