House build Gantt chart template
A residential build from site set-out to practical completion. Use it as a starting point for a new home, from site set-out and slab to practical completion, with the frame inspection marked as a milestone.
It has 4 phases, 15 tasks and 2 milestones, joined by 18 links, and runs for 53 working days on a Monday to Friday week. The template opens below in the free Gantt chart maker, starting today. Change any task, then export a PNG, PDF or CSV or share a link. No account is needed.
- Free, no sign-up
- Tasks already linked
- Critical path shown
- Export PNG, PDF and CSV
Tasks in the house build template
Durations are in working days. Predecessors use the tool's row numbers: 3 means “starts after row 3 finishes”, and 4SS+2 means “starts two working days after row 4 starts”. A phase shows the span of the tasks inside it.
| Row | Task | Type | Duration (working days) | Predecessors | Owner |
|---|---|---|---|---|---|
| 1 | Site and slab | Phase | 12 | ||
| 2 | Site set-out and earthworks | Task | 3 | Civil contractor | |
| 3 | Underground plumbing | Task | 2 | 2 | Plumber |
| 4 | Slab pour | Task | 2 | 3 | Concreter |
| 5 | Slab cure | Task | 5 | 4 | |
| 6 | Frame and roof | Phase | 13 | ||
| 7 | Wall and roof frames | Task | 8 | 5 | Carpenter |
| 8 | Frame inspection | Milestone | 0 | 7 | Certifier |
| 9 | Roof cover | Task | 4 | 8 | Roofer |
| 10 | Windows and external doors | Task | 3 | 9SS+2 | |
| 11 | Lock-up and services | Phase | 12 | ||
| 12 | External cladding or brickwork | Task | 10 | 10 | |
| 13 | Electrical and plumbing rough-in | Task | 5 | 9 | |
| 14 | Insulation and plasterboard | Task | 7 | 13 | |
| 15 | Fit-out | Phase | 18 | ||
| 16 | Cabinetry and tiling | Task | 10 | 14 | |
| 17 | Painting | Task | 6 | 16SS+4 | |
| 18 | Fit-off electrical and plumbing | Task | 4 | 16 | |
| 19 | Driveway and landscaping | Task | 5 | 12 | |
| 20 | Final inspection and defects | Task | 3 | 17, 18, 19 | |
| 21 | Practical completion | Milestone | 0 | 20 |
Scroll the table sideways to see every column.
How to use this template
- 1. Set the dates. Move a task later and the tasks linked after it move with it. Weekends are skipped.
- 2. Rename and resize the tasks. Type over any task name or duration, add your own tasks and delete the ones you do not need.
- 3. Check the critical path. Tasks in red have no float. A delay to any of them moves the finish date.
- 4. Export or share. Download a PNG, PDF or CSV, or copy a share link. The chart also saves in this browser as you work.
If you already have a chart saved in this browser, the tool opens your chart and offers to load this template instead, so nothing is replaced without asking.
Run the schedule in TaskRox
The free tool is for one person planning one chart. TaskRox is construction project management software: the whole team works on the same live schedule, with baselines, Microsoft Project and Primavera P6 import, and schedule tasks linked to RFIs and daily reports.
Other Gantt chart templates
- Simple project plan Gantt chart template
- Product launch Gantt chart template
- Event plan Gantt chart template
- Software release Gantt chart template
- Civil roadworks Gantt chart template
- Commercial fit-out Gantt chart template
- Construction programme Gantt chart template
- 3-week lookahead Gantt chart template
- Free online Gantt chart maker