House build Gantt chart template

A residential build from site set-out to practical completion. Use it as a starting point for a new home, from site set-out and slab to practical completion, with the frame inspection marked as a milestone.

It has 4 phases, 15 tasks and 2 milestones, joined by 18 links, and runs for 53 working days on a Monday to Friday week. The template opens below in the free Gantt chart maker, starting today. Change any task, then export a PNG, PDF or CSV or share a link. No account is needed.

  • Free, no sign-up
  • Tasks already linked
  • Critical path shown
  • Export PNG, PDF and CSV
Loading the Gantt chart maker…

Tasks in the house build template

Durations are in working days. Predecessors use the tool's row numbers: 3 means “starts after row 3 finishes”, and 4SS+2 means “starts two working days after row 4 starts”. A phase shows the span of the tasks inside it.

RowTaskTypeDuration (working days)PredecessorsOwner
1Site and slabPhase12
2Site set-out and earthworksTask3Civil contractor
3Underground plumbingTask22Plumber
4Slab pourTask23Concreter
5Slab cureTask54
6Frame and roofPhase13
7Wall and roof framesTask85Carpenter
8Frame inspectionMilestone07Certifier
9Roof coverTask48Roofer
10Windows and external doorsTask39SS+2
11Lock-up and servicesPhase12
12External cladding or brickworkTask1010
13Electrical and plumbing rough-inTask59
14Insulation and plasterboardTask713
15Fit-outPhase18
16Cabinetry and tilingTask1014
17PaintingTask616SS+4
18Fit-off electrical and plumbingTask416
19Driveway and landscapingTask512
20Final inspection and defectsTask317, 18, 19
21Practical completionMilestone020

Scroll the table sideways to see every column.

How to use this template

  1. 1. Set the dates. Move a task later and the tasks linked after it move with it. Weekends are skipped.
  2. 2. Rename and resize the tasks. Type over any task name or duration, add your own tasks and delete the ones you do not need.
  3. 3. Check the critical path. Tasks in red have no float. A delay to any of them moves the finish date.
  4. 4. Export or share. Download a PNG, PDF or CSV, or copy a share link. The chart also saves in this browser as you work.

If you already have a chart saved in this browser, the tool opens your chart and offers to load this template instead, so nothing is replaced without asking.

Run the schedule in TaskRox

The free tool is for one person planning one chart. TaskRox is construction project management software: the whole team works on the same live schedule, with baselines, Microsoft Project and Primavera P6 import, and schedule tasks linked to RFIs and daily reports.

Save your chart to TaskRox 14-day free trial, no credit card.