Commercial fit-out Gantt chart template

Office fit-out from strip-out to handover, with services and joinery. Use it for an office or retail fit-out where design approval, long-lead procurement and services rough-in decide when the space can be handed over.

It has 3 phases, 10 tasks and 1 milestone, joined by 11 links, and runs for 43 working days on a Monday to Friday week. The template opens below in the free Gantt chart maker, starting today. Change any task, then export a PNG, PDF or CSV or share a link. No account is needed.

  • Free, no sign-up
  • Tasks already linked
  • Critical path shown
  • Export PNG, PDF and CSV
Loading the Gantt chart maker…

Tasks in the commercial fit-out template

Durations are in working days. Predecessors use the tool's row numbers: 3 means “starts after row 3 finishes”, and 4SS+2 means “starts two working days after row 4 starts”. A phase shows the span of the tasks inside it.

RowTaskTypeDuration (working days)Predecessors
1Pre-constructionPhase25
2Design and approvalsTask10
3Long-lead procurementTask202SS+5
4ConstructionPhase28
5Strip-outTask52
6Partition framingTask65
7Mechanical, electrical and fire services rough-inTask86SS+2
8CeilingsTask57
9Joinery installTask53, 8
10Painting and floor finishesTask69SS+2
11HandoverPhase5
12Services commissioningTask310
13Defects inspectionTask212
14Handover to clientMilestone013

Scroll the table sideways to see every column.

How to use this template

  1. 1. Set the dates. Move a task later and the tasks linked after it move with it. Weekends are skipped.
  2. 2. Rename and resize the tasks. Type over any task name or duration, add your own tasks and delete the ones you do not need.
  3. 3. Check the critical path. Tasks in red have no float. A delay to any of them moves the finish date.
  4. 4. Export or share. Download a PNG, PDF or CSV, or copy a share link. The chart also saves in this browser as you work.

If you already have a chart saved in this browser, the tool opens your chart and offers to load this template instead, so nothing is replaced without asking.

Run the schedule in TaskRox

The free tool is for one person planning one chart. TaskRox is construction project management software: the whole team works on the same live schedule, with baselines, Microsoft Project and Primavera P6 import, and schedule tasks linked to RFIs and daily reports.

Save your chart to TaskRox 14-day free trial, no credit card.