Construction programme Gantt chart template

A head contractor master programme for a low-rise commercial building, from contract award to practical completion. Use it as the outline of a master programme for a two-storey commercial building: design and approvals, long-lead procurement, substructure, structure, envelope, services, finishes and handover.

It has 7 phases, 21 tasks and 5 milestones, joined by 31 links, and runs for 236 working days on a Monday to Friday week. The template opens below in the free Gantt chart maker, starting today. Change any task, then export a PNG, PDF or CSV or share a link. No account is needed.

  • Free, no sign-up
  • Tasks already linked
  • Critical path shown
  • Export PNG, PDF and CSV
Loading the Gantt chart maker…

Tasks in the construction programme template

Durations are in working days. Predecessors use the tool's row numbers: 3 means “starts after row 3 finishes”, and 4SS+2 means “starts two working days after row 4 starts”. A phase shows the span of the tasks inside it.

RowTaskTypeDuration (working days)PredecessorsOwner
1Pre-constructionPhase81
2Contract awardMilestone0Client
3Design development and documentationTask402Design team
4Building approvalTask203Certifier
5Long-lead procurement: lifts, switchboards and facadeTask603SS+20
6Site establishmentPhase15
7Site establishment and hoardingTask104
8Demolition and site clearingTask107SS+5
9SubstructurePhase45
10Bulk excavationTask158Civil contractor
11PilingTask1510SS+5Piling contractor
12Pile caps, footings and ground beamsTask1511
13Ground floor slabTask1012Concreter
14SuperstructurePhase40
15Level 1 columns and slabTask1513
16Level 2 columns and slabTask1515
17Roof structureTask1016
18Structure completeMilestone017
19EnvelopePhase30
20Facade installationTask305, 16SS+5Facade contractor
21Roofing and waterproofingTask1017Roofer
22Building weathertightMilestone020, 21
23Services and finishesPhase85
24Mechanical, electrical, hydraulic and fire services rough-inTask4015SS+10
25Lift installationTask255, 18Lift contractor
26Internal walls and ceilingsTask3022, 24SS+15
27Joinery, floor finishes and paintingTask3026SS+15
28Services fit-offTask1527SS+10
29Commissioning and handoverPhase25
30Testing and commissioningTask1525, 28
31Defects inspection and rectificationTask1027, 30
32Final building inspectionMilestone031Certifier
33Practical completionMilestone032

Scroll the table sideways to see every column.

How to use this template

  1. 1. Set the dates. Move a task later and the tasks linked after it move with it. Weekends are skipped.
  2. 2. Rename and resize the tasks. Type over any task name or duration, add your own tasks and delete the ones you do not need.
  3. 3. Check the critical path. Tasks in red have no float. A delay to any of them moves the finish date.
  4. 4. Export or share. Download a PNG, PDF or CSV, or copy a share link. The chart also saves in this browser as you work.

If you already have a chart saved in this browser, the tool opens your chart and offers to load this template instead, so nothing is replaced without asking.

Run the schedule in TaskRox

The free tool is for one person planning one chart. TaskRox is construction project management software: the whole team works on the same live schedule, with baselines, Microsoft Project and Primavera P6 import, and schedule tasks linked to RFIs and daily reports.

Save your chart to TaskRox 14-day free trial, no credit card.