Civil roadworks Gantt chart template

Road upgrade with traffic management, drainage, pavement and hold points. Use it for a road or pavement upgrade where drainage, subgrade and pavement layers follow each other and inspections are marked as hold points.

It has 4 phases, 11 tasks and 4 milestones, joined by 16 links, and runs for 40 working days on a Monday to Friday week. The template opens below in the free Gantt chart maker, starting today. Change any task, then export a PNG, PDF or CSV or share a link. No account is needed.

  • Free, no sign-up
  • Tasks already linked
  • Critical path shown
  • Export PNG, PDF and CSV
Loading the Gantt chart maker…

Tasks in the civil roadworks template

Durations are in working days. Predecessors use the tool's row numbers: 3 means “starts after row 3 finishes”, and 4SS+2 means “starts two working days after row 4 starts”. A phase shows the span of the tasks inside it.

RowTaskTypeDuration (working days)Predecessors
1MobilisationPhase6
2Possession of siteMilestone0
3Traffic management set-upTask22
4Service locating and potholingTask33
5DrainagePhase14
6Stormwater pipes and pitsTask124
7Hold point: pipe bedding inspectionMilestone06SS+3
8Backfill and compaction testingTask66FF+2
9PavementPhase17
10Subgrade preparationTask58
11Hold point: subgrade proof rollMilestone010
12Sub-base and base courseTask811
13Kerb and channelTask612SS+3
14Asphalt surfacingTask312, 13
15FinishingPhase6
16Line marking and signageTask214
17Topsoil and seedingTask414SS
18Traffic management removedTask116
19Practical completionMilestone017, 18

Scroll the table sideways to see every column.

How to use this template

  1. 1. Set the dates. Move a task later and the tasks linked after it move with it. Weekends are skipped.
  2. 2. Rename and resize the tasks. Type over any task name or duration, add your own tasks and delete the ones you do not need.
  3. 3. Check the critical path. Tasks in red have no float. A delay to any of them moves the finish date.
  4. 4. Export or share. Download a PNG, PDF or CSV, or copy a share link. The chart also saves in this browser as you work.

If you already have a chart saved in this browser, the tool opens your chart and offers to load this template instead, so nothing is replaced without asking.

Run the schedule in TaskRox